Making Sense of Seattle’s Center City Streetcar Mess

Will the new streetcar vehicles fit on the tracks? In the city's maintenance barns? What is happening here?

By Kevin Schofield July 25, 2018

Seattle, WA, USA Feb. 17, 2017: Riders prepare to board an orange colored South Lake Union Trolley on a sunny winter day in Seattle, Washington

Weve been waiting months for a consultant report on the Center City Streetcar project, since Mayor Durkan put it on hold pending financial review earlier this year. But the end of June deadline for that report has come and gone.

In the meantime, Durkan let slip a detail in a KUOW interview that has snowballed into speculation about how badly the project has gone off the rails even in the face of strong political support to see the project through to completion.

On July 5, Durkan sat down with KUOWs Bill Radke for an interview. Heres what she had to say on the topic of the Center City Streetcar and the pending review: (emphasis mine)

Durkan: So theres two problems with the streetcar project that we posit. First, we didnt know how much it was going to cost to build it. The very … the estimates were millions and millions of dollars apart. Second, we didnt know how much it was going to cost to operate it they too were million dollars spreads. So we believe that the public has a right to know before they embark on such a big project, how much will it cost to build, how much will it cost to operate. We had a preliminary review, KPMG came and briefed, there were some questions they still hadnt answered that they need to go back and look at. For example, one of the things that we know is that the streetcar, the new streetcars as designed, are longer than the current ones we have and heavier. They wont fit in the maintenance barns, for example, and were not sure they can fit on the gauge of rail thats there. So we need before we start a project like that, to know how much is it going to cost to build, how much is it going to cost to operate, and how many people will it really move, because the goal of transit has got to be to move as many people through Seattle as we can…

Radke: So are you saying it could be that Seattle will not build the line to connect the two existing streetcar lines? That still might not happen?

Durkan: That still might not happen. Were looking at the options, and there may be other options that are available to connect those two things that wont be a continuous route. Were in the process now of looking at both the technical data, the ridership estimates, and also what will it do for, theres a lot of businesses up and down First Avenue because we did utilities work that was necessary some of those pipes were wooden but tearing up those streets takes a heavy toll on those businesses as well. So were looking at all those factors.

Eleven days later, KIRO reported that quote as part of a longer story on the streetcar issues. That caught the eye of Council member Lisa Herbold, and last Friday in her weekly newsletter to constituents she said that she had asked Council staff to look into the matter: (emphasis mine)

While we are awaiting the results of the independent review of the Center City Streetcar ordered by the Mayor a media report noted that the new streetcars as designed wont fit in the existing maintenance barns, and that there may be an issue of whether they fit the gauge of rail.

Council Central Staff, on my request, has verified the accuracy of this report; it appears the error will require either a change order for the design of the streetcars or incur new costs for construction of new or retrofitted maintenance barns. I am requesting that the Mayors Streetcar Assessment include full transparency in the added costs for this unfortunate error.

Its disappointing to hear thisthese issues of accountability need to be dealt with much earlier, and they highlight the need for the increased Capital Project Oversight the Council has been working on.

Yesterday the Seattle Times jumped in, diving a bit more into the specifications for the new streetcars. And that prompted Mayor Durkans office to issue their own statement on the status of the review. It notes that there is a funding shortfall (previously reported) for the project, and that the consultant review (by KPMG) is ongoing. It adds:

Concurrently with KPMGs review, the Durkan Administration has also learned that:

  • – The streetcar vehicles procured for the C3 are heavier, longer and wider than the existing SLU and First Hill streetcars;
  • – There may be additional capital shortfall to complete building the C3 line; an
  • – There needs to be an updated assessment of the O&M costs for the existing SLU and First Hill streetcar lines.

In August, it is hoped that KPMG will finalize their report to provide their independent analysis of the project. The KPMG analysis was much more complex than initially expected including the review of thousands of estimates, design materials and correspondence. The report will provide a fact-based review of costs, ridership, opportunities and challenges with building and operating the C3 streetcar.

The report has raised a series of questions including:

  • – What are the capital costs of building the C3 streetcar?
  • – What are the capital costs of utility relocations?
  • – What are the costs of delaying construction until future years?
  • – What are current and forecasted O&M costs of the SLU, First Hill and C3 streetcar lines?
  • – What are the current ridership numbers and future ridership assumptions on the current lines as well as C3?
  • – Given actual and projected ridership and farebox collections, and projected O&M costs, will there likely be ongoing budget shortfalls and if so, how much?
  • – What are the ongoing O&M subsidies from partner agencies and businesses?

In addition, further questions not initially anticipated were raised regarding the entire streetcar system:

  • Are there ways to reduce O&M costs while optimizing ridership on the C3 line?
  • What are the long-term financial projections, including subsidies, for the streetcar?
  • If O&M subsidies decrease or cease, what are the expected budget implications for current lines as well as the C3 line?

We are hopeful that the KPMG report will address nearly all of these questions.

As a result of uncovering the challenges with the vehicle contract, a series of complex technical and engineering questions have been raised. While these challenges became a general factor as part of KPMGs review, a more detailed engineering review is critical to understanding the cost and feasibility of the project. Many of these additional questions could have further impacts on the capital costs of this project:

  • – How does the increased weight of the new cars impact the current system? Can the full streetcar route handle the additional weight of the cars?
  • – How does the length of the new cars interact with the current system?
  • – How does the width and length of the new cars impact the maintenance barn?
  • – Does the width of the new cars impact the current system?
  • – How does the size of the cars impact the design of the proposed stations as well as current stations?
  • – Are the new vehicles compatible with the current track gauge? If not, what options, costs and disruptions to service would there be for retrofitting the tracks?

Theres a lot of talking in this series of events, but little actual information, a fair amount of speculation, and an abundance of questions. Lets unpack it a bit, starting with the gauge of the track.

Railroad track gauge (the width between the tracks) is a well-known and well-established standard in the United States, 1.435 meters, dating back nearly 200 years to the United Kingdom.

The Seattle Times provided a link to the specifications document for the new streetcars. The document shows that the track gauge for the streetcars was written to the official standard. So if the cars are manufactured to a different gauge which would be stunning given the wide application of the standard that would be a manufacturing error, not the citys mistake.

That said, the spec also allows the new streetcars to be longer and wider than the ones currently in use on the First Hill and SLU lines, as well as heavier. It also precisely specifies the platform interface, the exact distance from the center-line of the cars to the platform edge as well as the height of the platform at the doors, which is required to ensure that the cars align properly with platforms. That needs to be the same as the existing cars.

The track gauge shouldnt be an issue. It may be that the tracks already installed on the First Hill and SLU lines may not be strong enough to support heavier cars, but thats a very different question.

And theres some precedent for that: When the bus tunnel was originally built, they used the wrong tracks and later needed to tear them up and replace them when Sound Transit was ready to start running trains through the tunnel. The update from Durkans office yesterday specifically asks whether the First Hill and SLU lines can support the weight of heavier cars.

It may be that the Mayor misspoke in her KUOW interview when she said that the track gauge was an issue, and conflated the width of the cars with the width of the track. Her statement yesterday reiterates that the new streetcars are heavier, longer and wider, but doesnt reach any conclusions about incompatibility with the track gauge (though it asks the question again).

However, there have been several recent mentions, including in Durkans statement, that longer and wider cars might not fit into the existing maintenance barn. If they dont fit, its an issue, but not an unsolvable one. A much more serious issue would be if longer and wider cars dont fit with the existing platforms and along the path of the existing lines and Durkans statement suggests they are looking at that was well.

However, the specifications document says that the platforms are 1.280 meters from the track centerline and the maximum vehicle width is 2.450 meters, which would make it 1.225 meters from the centerline so as long as its built to specification, the platforms shouldnt be an issue either.

These are very technical questions, but ones that can be answered and verified with great precision by engineers such as the ones KPMG is using to conduct its review. A constant trickle of incomplete information makes for some good headlines, but doesnt lead to good decision-making about the future of the project, so as frustrating as it is to wait for a delayed report before reaching conclusions as to what should happen with the project, thats the best course of action.

Nevertheless, a group of businesses calling themselves the Seattle Streetcar Coalition sent the Mayor a letter last month urging the Mayor to let the project go forward, while The Urbanist speculates on what the report says, claims that the Mayor has refused to meet with the group, and accuses her of an anti-transit bias.

The statement from the Mayors Office yesterday said that they plan to be transparent about the findings of the consultant and the citys internal review:

To ensure full transparency and accountability in this project, the City will be releasing the KPMG report to the public once finalized. The Mayor has heard a range of opinions and questions on the project including from many businesses in downtown Seattle. She wants to continue to hear from the public and stakeholders as the KPMG report and engineering updates are released, so all stakeholders have the full details and facts regarding the project. No final decision will be made until budget, feasibility, and community impacts are understood.

They hope the KPMG report will be finished next month. Stay tuned, and try to reserve judgment until we have better, and more complete, information. At that point, it should become clear whether the Mayor was justified in delaying the project to conduct a review, and it should be easier to evaluate the options on how to move forward, incorporating technical, financial, transportation, political, economic and community considerations.